[Skip to Content]
Wall Volunteer Fire Department - Homepage

Wall VFD Station 2

New Substation Location is: 2650 S US 87 

3-23-22 Land donated for the new substation,Thank you Lord!

6-14-22 Driveway off of 87 South almost complete.

7-14-22 Pad work has started!

8-18-22 Rebar and plumbing in place.

8-20-22 Blessed with base material for the substation!

8-24-22 Poured main slab with great weather.

9-07-22 Poured approach and almost framed up!

9-14-22 Tin is on. Drone Shots added, thanks Joey! 

10-11-22 Rain water storage completed, let it rain!

10-20-22 Insulated and painted.

12-06-22 Nearing completion!

12-07-22 Not open yet, but the lights are on.

12-22-22 Open For Calls!

03-27-2023 Septic system completed, thank you Sefcik Construction for you generous donation!

04-26-2023 Station sign installed, Thank you FASTSIGNS!

 

  • Land - IMG 6475
  • Driverway Construction
  • 87a Driveway Construction
    Driveway off of 87 South.
  • 20220714-1 Pad Work
    Pad Work has started!
  • Nearly ready for the pour!
    Nearly ready for the cement!
  • Drains and rebar in place.
    Drains and rebar in place.
  • Plumbing in place.
    Plumbing in place.
  • The good Lord has blessed Wall VFD again!
    The good Lord has blessed Wall VFD again!
  • Thank you Primoris Renewable Energy for the base material for our substation!
    Thank you Primoris Energy for providing our base material!
  • Thank you JRD Construction Services for helping Wall VFD!
    Thanks to Tanner Dunn and Matt Forkner with JRD Construction for all of their help!